Your building control approver has been wound up: what designers and developers should do

A wound-up building control approver is a registered building control approver that a court has ordered into liquidation, so it can no longer supervise your project. It matters because live projects must move to another approver, the local authority or the Building Safety Regulator, often with delay and extra cost.

In short

When a registered building control approver is wound up, projects that are not higher-risk buildings move to a new approver appointed in time or revert to the local authority. Higher-risk building projects revert to the Building Safety Regulator, and in the Assent case owners had to stop work until the regulator confirmed a valid application. Expect extra fees and possible reassessment of completed work. Gather your records, act within the seven-day window and tell your contract works, warranty and PI insurers.

The short answer: who takes over your project

When a registered building control approver (RBCA) is wound up, it can no longer supervise live work. Projects that are not higher-risk buildings move to another RBCA if the owner appoints one in time, or otherwise revert to the local authority. Higher-risk building projects revert to the Building Safety Regulator (BSR). The table below follows the government's operational notice for the Assent case; the details in any future case may differ.

ProjectWho takes overCan work continue?Time limit
Not a higher-risk buildingA new RBCA chosen by the owner, otherwise the local authorityYes, but the work must be inspected7 days from a cancellation notice to appoint a new RBCA, which must then give an initial notice within 7 days
Higher-risk buildingThe BSRNo; stop until the BSR issues a notice of valid applicationApply to the BSR for building control approval to restart

Under section 52 of the Building Act 1984, the outgoing approver gives cancellation notices for live projects. Any part final certificates already issued remain valid, according to the notice.

What reversion to the local authority involves

The government's reversion FAQs explain that responsibility for compliance sits with the person carrying out the work. Key points:

In practice this means drawings, specifications, inspection records and photos become valuable. Designers and contractors who hold them will usually be asked for them, sometimes at short notice.

The Assent example and higher-risk buildings

On 6 November 2025 the court made winding-up orders against Assent Building Control Compliance Limited, LB Building Control Limited and Oculus Building Consultancy Limited, with the Official Receiver as liquidator. The BSR bulletin of 1 December 2025 confirmed that all higher-risk building projects would revert to the BSR, and that other projects would go back to the local authority unless an alternative RBCA was chosen.

For new buildings, the government's higher-risk building criteria cover buildings at least 18 metres high or with at least seven storeys that contain at least two residential units, as well as hospitals and care homes meeting the same height test. These are overseen directly by the BSR. See our guides to the higher-risk building regime and the single construction regulator.

Insurance points for developers, contractors and designers

An approver failure is mainly a regulatory and programme problem, but it can touch several policies. Cover depends on each policy's terms.

CoverWhy it may matterWhat to check
Contract worksA stop on site extends the programme and the period the works are exposed.Policy period, any extension, site security conditions during a pause.
Delay in start-upDevelopers lose income if completion slips.Most delay covers are triggered by insured physical damage, so a regulatory delay alone is usually not covered.
Designers' PIClients may claim for delay or redesign if an approver or regulator finds non-compliant design.Notify circumstances promptly; see PI and delay claims.
Latent defects or structural warrantyProviders commonly rely on building control sign-off or their own technical audit.Tell the provider about the change and any conditions before completion.
Approver's own PIA claim against a wound-up approver may need to go to its insurer.The Third Parties (Rights against Insurers) Act 2010 may let a claimant pursue the insurer directly; take legal advice.

Contractors with design responsibility should read PI for in-house design teams. Approvers themselves can read PI for registered building control approvers.

Illustrative examples

These examples are illustrative, not real cases.

Small developer, four houses

The developer receives a cancellation notice and appoints a new RBCA within seven days. The new approver asks for inspection records and photos of concealed work. Some foundations have to be exposed for checking, adding cost and two weeks to the programme.

Residential block over 18 metres

Work stops while the client applies to the BSR. The main contractor's programme slips and the client asks its broker to check the contract works period and its developer PI position on design changes requested by the regulator.

Architect on a reverted scheme

The local authority queries a fire stopping detail the previous approver had accepted. The architect notifies the matter to its PI insurer as a circumstance and records the advice given; see notifying a circumstance.

Common mistakes

Practical steps

  1. Confirm whether the project is a higher-risk building and who now regulates it.
  2. Decide quickly whether to appoint a new RBCA or accept reversion.
  3. Request project information from the liquidator as the notice describes.
  4. Gather drawings, specifications, inspection records and photos.
  5. Review appointments and building contracts for who bears delay and extra fees; see JCT and NEC appointment terms.
  6. Tell your broker so contract works, warranty and PI positions can be checked.

For wider cover, see our commercial insurance hub and construction insurance guide. Apex arranges construction and professional indemnity insurance for UK firms; a broker reads every enquiry.

Sources

Frequently asked

My building control approver has gone bust. Who signs off my project?

For projects that are not higher-risk buildings, another registered building control approver if you appoint one in time, otherwise the local authority, which issues the completion certificate. Higher-risk building projects revert to the Building Safety Regulator. In the Assent case, owners had seven days from a cancellation notice to appoint a new approver.

Do I have to stop work on site?

For projects that are not higher-risk buildings, the Assent notice said work could continue but must be inspected. For higher-risk building projects it said owners must stop work until the Building Safety Regulator issues a notice of valid application. Check the notice for your case, as arrangements may differ.

Will I have to pay building control fees again?

Often there is extra cost. Government reversion guidance says the local authority charges for reverted work under its charging schedule and that costs are likely to be additional, because it must check work already done. Whether you can recover fees already paid to a failed approver depends on the insolvency process.

Does insurance cover delay caused by building control failure?

Usually not directly. Delay in start-up covers are commonly triggered by insured physical damage, not regulatory delay. Designers' PI may respond to a client's claim if the delay arises from negligent design, subject to the policy terms. Notify your insurers early and ask your broker to review each policy.

Are certificates already issued by the old approver still valid?

The Assent operational notice says any part final certificates already issued remain valid, and owners should tell the BSR about them where relevant. Work not yet certified may be reassessed by the new approver, the local authority or the regulator.

Mid-sized business? Get a second opinion on your programme

Send us your current schedules or renewal pack and we will review the whole programme and tell you plainly what to keep and what to change. No fee and no obligation. Or call 0117 325 0027.

Get a second opinion Get a quote

Apex Insurance Brokers Limited is authorised and regulated by the Financial Conduct Authority. Registered in England and Wales, company number 07014570. This page is general information, not advice on your individual circumstances, and it does not guarantee that cover will be available or on what terms.